ORDINANCE NUMBER 1396

APPENDIX A-1

PROCEDURE OUTLINE FOR DRAINAGE PLAN APPROVAL
(See Section 2 for detailed information)

Applicant may begin with step 1 or step 5.

  1. Submit preliminary plans and application
    {21 days prior to Step 3}
  2. Review by City Sewer Superintendent
  3. Action by Sanitary Board of Trustees

    A-1-1
    1. Conditional Approval:
      {Go to Step 4 or 5}
    2. Approval:
      {Go to Step 4 or 5}
    3. Disapproval:
      {Go back to Step 1}
    4. Refer to Sewer Superintendent:
      {Go to Step 3}
  4. Grading and installation of drainage features
    {Go to Step 5}
  5. Submit final plans and application
    {21 days prior to Step 8}
  6. Review by City Sewer Superintendent
  7. Financial guarantees
  8. Action by Sanitary Board of Trustees
    1. Conditional Approval:
      {Go to Step 9}
    2. Approval:
      {Go to Step 9}
    3. Disapproval:
      {Go back to Step 1}
    4. Refer to Sewer Superintendent:
      {Go to Step 8}
  9. Construction completed
  10. File completion affidavit and "As Built" plans
  11. Review for compliance by Sewer Superintendent
    {30 days after Step 10}
  12. Bond termination {60 days after Step 10}

This outline is for guidance only and not a part of this Ordinance.